Projects
Construction Projects
Grafton Road Drinking Water Treatment Facility
Upgrade water treatment facility for the Haven, Smith, and Harrison Wells which serve the Pease Tradeport drinking water system. These wells were found to be contaminated with PFAS compounds in 2014. The Haven Well had levels above the drinking water advisory standard and has been off-line since 2014. An activated carbon filter system was installed in September 2016 to treat the Smith and Harrison Wells. The US Air Force has authorized funds for the City of Portsmouth to design and construct the final treatment system that will treat water from the Smith, Harrison, and Haven Wells. Construction began April 2019.
Status: Under Construction
Project Manager: Al Pratt, Water Resource Manager 520 - 0622
Estimated Start Date: Construction: Spring 2019
Estimated Time of Completion: 2021
Estimated Cost: $14,300,000
Funding Source: The Air Force is reimbursing the City for the capital costs associated with these projects because the cause of the contamination was due to firefighting foam used by the Air Force when Pease Air Base was active from the 1950's to the 1990's.
Designer/Contractor: Weston & Sampson/Kinsmen Corporation
Newington Booster Pump Station Upgrade
This project will upgrade the building and pumps at the Newington Booster Station and also install aeration in the Newington Booster water storage tank to improve the water quality going into the Portsmouth water distribution system.
Status: Under Construction
Project Manager: Al Pratt, Water Resource Manager 520 - 0622
Estimated Start Date: Summer 2018
Estimated Time of Completion: April 2020
Estimated Cost: $3,630,000
Funding Source: Capital Improvement Funds
Designer/Contractor: Stantec/Methuen Construction
Upcoming Projects
Water Mains across Little Bay
This project consists of design and construction of water transmission mains beneath Little Bay to replace existing mains. Preliminary investigations of the existing water mains and valves have identified degraded conditions. Due to the importance of this water main, this project is necessary to ensure water is continuously supplied from Madbury to Portsmouth and service is not disrupted.
Status: Design began in 2018 with construction to occur at a later date. Design will assure that the water system has contingency plans in place should the transmission main fail prior to replacement.
Project Manager: Al Pratt, Water Resource Manager 520 - 0622
Estimated Start Date: Design: 2020
Estimated Time of Completion: Design 2019
Estimated Cost: Engineering & Design: $750,000
Funding Source: Capital Improvement Funds
Designer/Contractor: Wright-Pierce/TBD
Madbury Well Improvements
The project consists of construction of upgrades of meters, controls, valving, and chemical feed equipment for the connection of the newly installed Well 4 and Well 5 replacement wells and upgrades to the existing wells #2 and #3 in the Madbury wellfield.
Status: In design
Project Manager: Al Pratt, Water Resource Manager 520 - 0622
Estimated Start Date: 2020
Estimated Time of Completion: 2021
Estimated Cost: $2,200,000
Funding Source: Capital Improvement Funds
Designer/Contractor: Underwood Engineers/TBD
New Groundwater Well
The purpose for this project is to drill test wells, determine well yields, and evaluate water quality and sustained yield potential with respect to the feasibility of developing a water supply source that improves the capacity of the Portsmouth water system. Additional work under subsequent projects may include construction of final production well(s), new source permitting, and the design and construction of treatment, pumping, and piping systems.
Status: A Request for Proposal for consultants to perform this work was issued in early 2017 and a consultant was selected. Test well drilling began in the Fall 2019.
Project Manager: Al Pratt, Water Resource Manager 520 – 0622
Estimated Start Date: January 2019
Estimated Time of Completion: TBD
Estimated Cost: $200,000
Funding Source: Capital Improvement Funds
Designer/Contractor: Consultant - Emery & Garrett Groundwater Investigations