Current Activity
Week of December 16th, 2019
Upcoming Work
A few minor clean-up activities will take place on Monday, with winter shutdown anticipated to be complete by the end of the day.
Water Service Interruptions
Water work is complete for this year. No water service interruptions are anticipated until work resumes in the spring.
Traffic Patterns
Traffic patterns have been restored to normal until work resumes in the spring.
Work Zone
General Notes
If you have any questions or concerns, please contact Ryan Flynn, construction Project Manager at 766-1413.
Construction Detour
Below is the current construction detour route which will be implemented daily during construction hours. To optimize business access, this route may be adjusted as the active work zone shifts within the project construction limits. All businesses will remain open during construction, and we encourage the community to continue supporting them.

Project Schedule
The following table lists public meetings and project milestones. If a specific date is not listed, the anticipated timeframe is indicated and the table will be updated as the project progresses.
November 2015 | Initial Public Information Meeting |
---|---|
Presentation Slide Show | |
Presentation Video | |
October 2016 | Presentation Slide Show |
Presentation Video | |
March 2017 | Roadway borings |
2017 | Finalized preliminary design |
2018 | Final design, bidding and award of contract |
February 20, 2019 | Public Meeting to review next phase of project |
April 25, 2019 | Preconstruction meeting for the public |
May 2019 | Start of Phase 1A construction - spanning Bartlett Street to the Route 1 Bypass |
Fall 2020 | Anticipated completion of Phase 1A construction |