Project # 8: Commerce Way Reconstruction
The project reconstructs Commerce Way to City standards in order for it to be accepted as a City Street. The water main under the road will also be replaced. The City has set up a betterment district in order for the current owner to pay for the upgrades through a municipal bond.

Project Manager: Dave Desfosses 766-1411
Estimated Start Date: Spring 2015
Estimated Time to Completion: 90 days
Estimated Cost: $1,400,000
Funding Source: Privately Funded
Contractor: TBD