Project #2: Lincoln Area Sewer Separation Contract 3B:
Project Description: This project is part of the City's on-going Combined Sewer Overflow-Long Term Control Plan. The project will include water, sewer, drainage and streetscape modifications on Richards Avenue from Middle Street to Lincoln Avenue; Miller Avenue from Middle Street to Lincoln Avenue; Broad Street from Lincoln Avenue to Merrimac Street; Rockland Street from Sherburne Avenue to Broad Street; Highland Street; and Merrimac Street to separate sewer lines. This project, required as part of an EPA Administrative Order, and is part of The City's comprehensive efforts to correct problem areas. For Updates Click Here
Project Manager: Rick Dolce 766-1413 / Terry Desmarais 766-1421
Estimated Start Date: Spring 2012
Estimated Time of Completion: Fall 2013
Estimated Cost: $5 Million
Funding Source: Sewer and Water System Revenues
Contractor: TBD