Fire Station Two - Photos and Updates
December 1, 2009 - Interior framing and duct work installation work being performed on the second floor.

December 1, 2009 - Exterior drainage, encased utility conduits, and concrete pads for both the emergency generator and transformer can been seen in this photo.

October 27, 2009 - Exterior brick work is completed on the south side of the station. Underground conduit is being laid for utilities.

October 27, 2009 - The apparatus floor is curing after concrete pour.
October 8, 2009 - Interior Framing: Framing of the interior begins on both the first and second floors.
October 8, 2009 - The apparatus bay is prepared for concrete pour.
September 2, 2009 - The final tier of forms are in place in the two stair towers
September 2, 2009 - The masons arrive and begin setting brick on the north wall.
August 27, 2009 - Roof decking is completed over the apparatus bays.

August 13, 2009-Apparatus bay walls and a majority of the training tower are in place awaiting concrete. Also a base coating of pavement was laid on site during the week
July 17, 2009 - Steel beams and trusses are placed on the first floor section of the support and training room areas of the station.
June 15, 2009 - An aerial photograph of the footprint of the new fire station
June 4, 2009 - Concrete pour of exterior frost walls

May 19, 2009 - Forms for the footings being constructed and positioned

May 6, 2009 - Site work is underway

|
 |
|