CITYWIDE PROJECTS 2003
8. Court Street Reconstruction Project
Update July 11, 2003
Court street construction continues with the installation of water main up Rogers street. Rogers Street will be closed to non local traffic during construction hours because of its limited width.
The drainage work has begun with some work on the edge of the South Mill Pond. A new drainage outlet is being constructed on the edge of the pond that will carry the rain water from the Court Street area.
Some sewer cleaning work will be taking place at the intersection of Parrott and Rogers next week as well.
return
Update June 19, 2003
Scope of Project
- Contractor: Gove Construction Services, Inc.
- Area of Work:
- Along Court Street from Middle to Pleasant
- Rogers Street from Court St. to Parrott Ave.
- Construction of new Water, Sewer and Storm Water Utilities
- Complete Road Reconstruction including sidewalks, curbs and street lighting
Sequence of Work
June
- Exploratory excavations will commence the last week in June.
July
- Roger’s Street:
- Court Street
- Continue water line from Roger’s to Middle Street
August
- Roger’s Street:
- Complete Drainage
- Complete Sewer
- Street Lighting
- Roadway Construction
- Court Street (Church to Pleasant)
September
- Roger’s Street:
- Complete Roadway Construction
- Curbing and Sidewalks
- Restoration and Clean-up
Court Street (Rogers to Pleasant)
- Drainage Construction
- Waterline Construction
- Begin Street Lighting Construction
- Begin Roadway Construction
- Court Street (Church to Pleasant)
- Complete Sewer Construction
October
- Court Street (Church to Pleasant)
- Complete Roadway Construction
- Complete Street Lighting
- Curbing and Sidewalks
- Restoration and Clean-up
- Court Street (Middle to Rogers)
- Begin Sewer Construction
- Begin Drainage Construction
November
- Court Street (Middle to Rogers)
- Complete Sewer Construction
- Complete Drainage Construction
- Street Lighting
- Roadway Construction
- Curbing and Sidewalks
- Restoration
- Middle Street
- Drainage
- Roadway Construction
- Curbing and Sidewalks
- Restoration
December
- Court Street and Middle Streets
- Complete Curbing and Sidewalks
- Restoration and Clean-up
Spring 2004
- Final Pavement, Landscaping and Clean-up
Notices
- Temporary disruption of Water and Sewer Services may be necessary.
- Notice will be provided before closing any street
- Resident Engineer will schedule with each business and resident to “dye test” sewer for new connections.
Traffic
- On-street parking will be maintained as practicable. May need to seek alternative parking at times.
- Alternating one way traffic will be maintained as possible on Court St.
- Pedestrian traffic will at a minimum be maintained on one side of the street. Access to businesses will be maintained.
This project is a major reworking of the Court Street corridor. The project includes replacing all existing utilities, adding a storm drain, a new roadway, new curbing and new sidewalks. Any questions regarding this project can be directed to Dave Desfosses at the Public Works Dept 766-1411.